Timeline


·         19 June 2007- The Victorian Government released its Water Plan project

·         30 July 2009- Winning bidder for construction, AquaSure was announced

·         6 October 2009- Construction commenced

·         4 February 2010- First sections of the new pipeline are laid

·         December 2011- Production and related operations expected to commence

·         2035-2045- Contract for the operation of the plant expected to expire